Prepare for your Contractor License Exam with our comprehensive quiz. Featuring multiple-choice questions and detailed explanations, this resource is designed to help you ace your exam and secure your license with confidence!

Practice this question and more.


Can contractors modify contracts unilaterally without any approval?

  1. Yes, if they believe it's necessary

  2. No, they must have the owner’s consent

  3. Only under emergency situations

  4. Only if the change is beneficial

The correct answer is: No, they must have the owner’s consent

In the context of contract law, unilateral modification of a contract by one party, such as a contractor, is generally not permissible without the consent of the other party involved, which in this case would be the owner. A contract represents a mutual agreement between parties, and any changes, amendments, or modifications to that agreement typically require the approval of all involved parties to be considered valid and enforceable. When a contractor wishes to modify a contract, they must seek agreement from the owner to ensure that both sides are aligned on the terms. This protects the rights and expectations of both parties and maintains the integrity of the contract. Allowing unilateral modifications could lead to disputes, misunderstandings, and potential legal issues, as one party might not agree with the modifications made by the other. The other choices imply conditions under which modifications might be acceptable, but they do not align with the standard legal understanding that modifications require consent from all parties involved.