Can a contractor change a specified material in the contract without permission from the owner?

  1. Yes, if it’s a minor change

  2. No, they need to get permission

  3. Only if it saves time

  4. Only if the owner is not reachable

The correct answer is: No, they need to get permission

A contractor must obtain permission from the owner before changing any specified materials in the contract. This requirement is essential to maintain the integrity of the contractual agreement and ensures that the owner retains some level of control over the project's specifications. Changes to materials can impact the overall quality, cost, and functionality of the project, which is why obtaining consent from the owner is crucial. This process helps to prevent misunderstandings and disputes that could arise from unilateral decisions made by the contractor. Additionally, contracts are legally binding documents, and adhering to their terms preserves the trust and professional relationship between the contractor and the owner.